Home > Outotec focuses on issues influencing type of support structure for flotation cells

Outotec focuses on issues influencing type of support structure for flotation cells

Supplier News

Outotec  outline the issues that influence the type of support structure for flotation cells used and provide a guide to the merits and demerits of the two major techniques used for providing the support.

The ever-increasing size of mineral processing operations has lead to the development of larger flotation cells, the largest of which now hold over 300 cubic metres of slurry.

Physically supporting these flotation cells in a minerals processing plant is now a challenge requiring significant engineering design and analysis.

Added to the engineering challenge is the economic one. Issues such as the availability of concrete or steel, labour costs and site topography will all have an influence on the cost of supporting the flotation cells.

Factors influencing support structure design

Climatic conditions

The two critical conditions related to the location of the plant are the prevailing winds and the seismic activity. Many mining regions are in areas of potentially high seismic activity and cyclonic winds, which makes the design of support structures more challenging.

The key issues when considering seismic loads are the slurry behaviour in the cell and the connection between the cell and the support structure.

Wind loads can also play a significant part with larger flotation cells presenting a substantial sail area with which to catch wind. This can apply a significant side load to the supporting structure.

The cells are not always full of slurry. Careful consideration of the connection between the structure and the cell is required to prevent empty tanks being dislodged during significant wind events.

Site location

The location of a mine can also impact the type of support structure used for flotation cells. Three key factors are the topography of the site, accessibility of the site for major construction equipment and personnel and the ground conditions at the site.

Flotation circuits generally have a series of steps between banks of flotation cells. These steps are necessary to provide the plant operators with the ability to control the flotation process.

The flotation tail is generally discharged to a tailings thickener, which is ideally done using a gravity discharge rather than a pump station, to reduce the ongoing operating cost.

Taking these two basic layout needs into consideration it can be seen that a gently sloping site for the construction of the plant is helpful with the flotation circuit inlet at the higher end and the tailings thickener at the lower end.

As it is rare to find a suitably sloped site, the creation of suitable topography through earthworks may be an option where the ground conditions allow this.

Ground conditions are also important when considering how to transfer the load of the flotation cells to the earth, which ultimately must support them.

In case of employing a discrete concrete mushroom cell support, the load is transferred to the ground in a relatively small footprint. This could be distributed further through a concrete sump floor in some cases.

Comparing this to a series of four footings on which a steel structure is constructed; these footings will take a proportion of the full load, thus reducing the strength required from the supporting ground.

Finally, the location of the proposed plant site also impacts on the availability of resources. Issues such as how the support structure will actually get to the site be it steel, pre-cast concrete or the raw materials for concrete production on site.

Mushroom cell support

Plant layout

A support structure should be designed to support the flotation cells, and not the other way around. In an ideal world, the flotation cells should be selected and laid out to optimise the operation of the plant.

Once the desired layout is established then a suitable support structure is designed. In reality, the two processes interact and will generally undergo several iterations.

Whilst compromise is necessary during this process, it is important that the operation of the flotation cells themselves is not compromised. Issues such as the height of the final cell discharge, number of steps in the floatation train and suitable access to services surrounding the cells must always be considered.

A supporting structure will be of no benefit, if there is insufficient head to drive the slurry through the plant.

Design of the flotation cells

There are two main types of flotation cell tanks with U-shaped bottom and flat bottom. The flotation cell tanks with flat bottom are also known as TankCells.

Issues such as the location and type of cell dump valve, any access doors into the larger TankCells and the type of slurry discharge valves will all influence the support structure design.

Though it would be unusual to support the U-shaped cells on purely concrete foundations, it could be done. These cells will clearly have different support needs.

The U-shaped cells have an inherently self-supporting base whilst the TankCells need support under the base of the cell. It is important to look closely at the loading information provided by the supplier when considering the type of support structure.

If TankCells are to be supported on steelwork, the spacing of the support beams is critical and is clearly impacted by the floor plate thickness of the tank.

Comparison of concrete and steel supports

The merits of using concrete in the support structure include the following:

  • Better access is provided under cells where cells are elevated above the plant floor area. Alternatively, for small numbers of cells the concrete bases may be directly on the floor.
  • Ability to use pre-cast concrete sections, reducing site construction time
  • More economic where concrete batching is readily available.

The demerits of using concrete in the support structure include the following:

  • Difficult to get levels sufficiently accurate (+/-5mm) without using a screed layer
  • Need to accurately cast–in allowances for any discharge valves or cell dump valves that protrude below the tank bottom
  • Availability of concrete is poor for remotely located operations.

The merits of using steel in support structure include the following:

  • Prefabrication offsite minimises site installation time
  • Easier to adjust site levels during installation
  • Higher flexibility when allowing for ancillary items

The demerits of using steel in support structure include the following:

  • More footing in the floor area, which can restrict access
  • Installation of steel structures can be expensive in some locations

Finally, it is important to consider that a combination of steel and concrete may prove to be the ideal solution in many cases.